Marcus A. Foster Building
Status: Substantially Complete
Location: 1011 Union Street, Oakland, CA 94607
Budget: $62 M
Funding Source: Bond Measures J and Y
Start Date: Quarter 1 (January - March) 2019
Completion Date: Quarter 2 (April - June) 2025
Scope: This project involves the demolition of existing structures, including a one-story building, a two-story building, and a portable structure, to facilitate the construction of a new 56,176 square feet (“SF”) two-story administration building to house OUSD Central staff. The redevelopment will incorporate comprehensive site improvements, including the installation of landscaping, safety fencing, and the redesign of parking lots and driveways to enhance traffic flow, accessibility, and safety.
Project Team:
Elena Comrie, Construction Manager
Christina Stone, Project Engineer
Harold Lowe, Outreach Partner
Project Schedule
| Planning | Quarter 1 (January - March) 2019 |
|---|---|
|
Design |
Quarter 3 (July - September) 2019 |
|
Bidding |
Quarter 2 (April - June) 2021 |
|
Construction |
Quarter 4 (October - December) 2021 |
| Closeout | Quarter 4 (October - December) 2024 |
Quarterly Reports
Quarter 3, 2025 (July - September) Report - Marcus A. Foster Building
Quarter 2, 2025 (April - June) Report - Marcus A. Foster Building
Quarter 1, 2025 (January - March) Report - Marcus A. Foster Building
Reports older than one (1) year are available by request through the California Public Records Act (PRA). Please email your request to publicrecords@ousd.org.