Roosevelt Middle School

Roosevelt Middle School Entrance

Project Description

This project will include the modernization of the main classroom building and auditorium to meet current safety guidelines and general improvements to the learning spaces throughout the building. During construction, students will continue learning uninterrupted while housed in a temporary portable classroom campus. Academics, athletics, EBAYC after-school learning, La Clinica health care, and food services will all be coordinated with to cause the least amount of disruption.

The project will be split up into three major parts:

  • Increment 1: Interim Housing and Science Modular Site Work
  • Increment 2: Interim Housing and Science Modular Buildings
  • School Modernization

STATUS:

Construction

BUDGET:

$91.55M, Measure J and Y funding

ADDRESS:

1926 East 19th Street, Oakland, CA 94606

ARCHITECT:

HKIT Architects

GENERAL CONTRACTOR:

Overaa

PROJECT TEAM:

Eric Scheuremann, Construction Manager

Ray Bermudez, Engagement Specialist

Announcements

There are no new announcements at this time. Check back soon for updates.

Project Schedule

Design

Phase 1: Quarter 2 (April - June) 2021

Phase 2: Quarter 1 (January - March) 2024

Bidding 

Quarter 2 (April - June) 2024

Construction (projected)

Quarter 3 (July - September) 2024

Completion (projected)

Quarter 2 (April - June) 2029

Quarterly Reports

Quarter 3 (July - September) Report - Roosevelt

Quarter 1 (January - March) Report - Roosevelt

 

Reports older than one (1) year are archived and available by request. To obtain an archived report, please email oaklandbuilt@ousd.org

 

Presentations

Project Advisory Committee Meeting - April 12th, 2023 | Presentation

Project Advisory Committee Meeting - March 29th, 2023 | Presentation

Project Advisory Committee Meeting - March 8th, 2023 | Presentation