Roosevelt Middle School
Project Description
This project is a phased construction that involves the modernization of the main building’s interiors, along with structural upgrades to enhance safety and functionality. A new 3,400 SF modular science building will be constructed, and the main building will undergo comprehensive upgrades, including right-sizing of classrooms, mechanical systems (heating, cooling, ventilation), plumbing, re-roofing, and lighting. Additionally, fire, intrusion, and sprinkler systems will be modernized. The scope also includes upgrades to outdoor spaces, site utilities, landscaping, and the garden area to improve campus aesthetics and functionality.
STATUS:
Construction
BUDGET:
$91.55M
FUNDING SOURCE:
Bond Measure B and Y
ADDRESS:
1926 East 19th Street, Oakland, CA 94606
ARCHITECT:
GENERAL CONTRACTOR:
PROJECT TEAM:
Eric Scheuremann, Construction Manager
Ray Bermudez, Engagement Specialist
Project Schedule
*Dates reflect the beginning of the phase.
Planning | Quarter 4 (October - December ) 2019 |
---|---|
Design |
Quarter 2 (April -June) 2021 |
Bidding |
Quarter 1 (January - March) 2023 |
Construction |
Quarter 2 (April - June) 2023 |
Completion (projected) |
Quarter 3 (July - September) 2029 |
Quarterly Reports
Quarter 1, 2025 (January - March) Report - Roosevelt
Quarter 4, 2024 (October - December) Report - Roosevelt
Quarter 3, 2024 (July - September) Report - Roosevelt
Reports older than one (1) year are archived and available by request. To obtain an archived report, please email oaklandbuilt@ousd.org.
Presentations
Project Pre-Construction Meeting - May 7th, 2025 | Presentation
Project Advisory Committee Meeting - April 12th, 2023 | Presentation
Project Advisory Committee Meeting - March 29th, 2023 | Presentation
Project Advisory Committee Meeting - March 8th, 2023 | Presentation