Roosevelt Middle School

Roosevelt Middle School Entrance

Project Description

Structural upgrades to the main building, including upgrades to the indoor spaces, mechanical heating, cooling, ventilation, plumbing, re-roofing, lighting, main entry, fire, intrusion, and sprinkler system. The work also includes right-sizing of classrooms and upgrades to outdoor spaces site utilities, landscaping, and garden.

STATUS:

Construction

BUDGET:

$91.55M, Measure B and Y funding

ADDRESS:

1926 East 19th Street, Oakland, CA 94606

ARCHITECT:

Noll & Tam Architects

GENERAL CONTRACTOR:

Overaa

PROJECT TEAM:

Eric Scheuremann, Construction Manager

Ray Bermudez, Engagement Specialist

Announcements

There are no new announcements at this time. Check back soon for updates.

Project Schedule

Design

Phase 1: Quarter 2 (April - June) 2021

Phase 2: Quarter 1 (January - March) 2024

Bidding 

Quarter 2 (April - June) 2024

Construction (projected)

Quarter 2 (April - June) 2025

Completion (projected)

Quarter 3 (July - September) 2027

Quarterly Reports

Quarter 4 (October - December) Report - Roosevelt

Quarter 3 (July - September) Report - Roosevelt

Quarter 1 (January - March) Report - Roosevelt

 

Reports older than one (1) year are archived and available by request. To obtain an archived report, please email oaklandbuilt@ousd.org

Presentations

Project Advisory Committee Meeting - April 12th, 2023 | Presentation

Project Advisory Committee Meeting - March 29th, 2023 | Presentation

Project Advisory Committee Meeting - March 8th, 2023 | Presentation