Roosevelt Middle School
Project Description
This project will include the modernization of the main classroom building and auditorium to meet current safety guidelines and general improvements to the learning spaces throughout the building. During construction, students will continue learning uninterrupted while housed in a temporary portable classroom campus. Academics, athletics, EBAYC after-school learning, La Clinica health care, and food services will all be coordinated with to cause the least amount of disruption.
The project will be split up into three major parts:
- Increment 1: Interim Housing and Science Modular Site Work
- Increment 2: Interim Housing and Science Modular Buildings
- School Modernization
STATUS:
Construction
BUDGET:
$91.55M, Measure J and Y funding
ADDRESS:
1926 East 19th Street, Oakland, CA 94606
ARCHITECT:
GENERAL CONTRACTOR:
PROJECT TEAM:
Eric Scheuremann, Construction Manager
Ray Bermudez, Engagement Specialist
Announcements
There are no new announcements at this time. Check back soon for updates.
Project Schedule
Design |
Phase 1: Quarter 2 (April - June) 2021 Phase 2: Quarter 1 (January - March) 2024 |
---|---|
Bidding |
Quarter 2 (April - June) 2024 |
Construction (projected) |
Quarter 3 (July - September) 2024 |
Completion (projected) |
Quarter 2 (April - June) 2029 |
Quarterly Reports
Quarter 3 (July - September) Report - Roosevelt
Quarter 1 (January - March) Report - Roosevelt
Reports older than one (1) year are archived and available by request. To obtain an archived report, please email oaklandbuilt@ousd.org.
Presentations
Project Advisory Committee Meeting - April 12th, 2023 | Presentation
Project Advisory Committee Meeting - March 29th, 2023 | Presentation
Project Advisory Committee Meeting - March 8th, 2023 | Presentation