McClymonds High School

McClymonds High School entrance

Project Description

Modernization of the McClymonds Campus focusing on 4 scope priorities:

Priority 1 Building Systems – Full Plumbing Replacement, HVAC modification including A/C, Electrical system upgrade, sprinkler system upgrade, seismic and security upgrades to the main building.


Priority 2 Indoor Space Upgrades – Upgrade to finishes of classrooms, labs, hallways, bathrooms, and cafeteria. Upgrades to gym locker rooms, coaches’ offices, dance and weight rooms and bathrooms. Including new furniture and equipment, and modified layouts.


Priority 3 Outdoor Space Upgrades – New scoreboard, grandstand with press box and outdoor bathrooms and concession stand at the football field. Upgrades to garden and plaza of peace. Reconfigured front and back ADA ramps. Modified perimeter fencing and landscaping.


Priority 4 Shop Renovations – Upgrades to finishes of the wood shop and creation of new engineering pathway lab next door. Seismic upgrades for the entire annex building.

STATUS:

Schematic Design

BUDGET:

$91.25 M, Measure Y funding

ADDRESS:

2607 Myrtle Street, Oakland, CA 94607

BRIDGING ARCHITECT:

Perkins Eastman

DESIGN ARCHITECT:

HKIT Architects

GENERAL CONTRACTOR:

Alten Construction

PROJECT TEAM:

Nicole Wells, Project Manager

Elena Comrie, Construction Manager

Christina Stone, Project Engineer

Harold Lowe, Outreach Partner

Announcements

There are no new announcements at this time. Check back soon for updates.

Project Schedule

Design (projected)

Quarter 3 (July - September) 2023

Bidding (projected)

Quarter 1 (January - March) 2025

Construction (projected)

Quarter 1 (January - March) 2026

Completion (projected)

Quarter 1 (January - March) 2027

Quarterly Reports

Quarter 3 (July - September) Report - McClymonds

Quarter 2 (April - June) Report - McClymonds

Quarter 1 (January - March) Report - McClymonds

 

Reports older than one (1) year are archived and available by request. To obtain an archived report, please email oaklandbuilt@ousd.org

 

Presentations

McClymonds Project Advisory Committee - November 7th, 2023 | Presentation, Meeting Summary

McClymonds Project Community Input Session - October 3rd, 2023 | Presentation, Meeting Summary, Q&A

McClymonds Project Advisory Committee - September 5th, 2023 | Presentation, Meeting Summary, Q&A

McClymonds Project Advisory Committee - August 1st, 2023 | Presentation, Meeting Summary, Q&A

McClymonds Project Community Input Session - June 6th, 2023 | PresentationMeeting Notes

McClymonds Project Advisory Committee - January 17th, 2023 | PresentationMeeting Notes

McClymonds Project Advisory Committee Meeting - October 4th, 2022 | PresentationMeeting Notes

McClymonds Project Advisory Committee Meeting - September 6th, 2022 | PresentationMeeting Notes

McClymonds Project Advisory Committee Meeting - June 7th, 2022 | PresentationMeeting Notes

McClymonds Community Input Session #2 - May 3rd, 2022 | PresentationMeeting Notes

McClymonds Project Advisory Committee Meeting - March 29th, 2022 | PresentationMeeting Notes

McClymonds Community Input Session - March 1st, 2022 | PresentationMeeting Notes

McClymonds Community Input Session - February 1st, 2022 | PresentationMeeting Notes

McClymonds Measure Y Academic Program Vision 2022 and Beyond | PresentationMeeting Notes