The project scope includes demolition of the existing CDC structure and replacement of a new CDC on the existing Laurel campus. The new CDC consists of four pre-school classrooms with the capacity to house 108 children. The front office includes a reception area, principal’s office, a parent resource center, staff workroom, warming kitchen, restrooms, and utility support spaces. Exterior site improvements include play yards, play structures, garden, artificial turf field and bio-swales. The design will meet energy and sustainability guidelines in the Collaborative for High Performance Schools (CHPS).
STATUS:
Complete
BUDGET:
$17.5M, Measures J and Y funding
ADDRESS:
3825 California St, Oakland, CA 94619
ARCHITECT:
GENERAL CONTRACTOR:
PROJECT TEAM:
Mary Ledezma, Project Manager
Imelda Meza, Project Engineer
Ray Bermudez, Engagement Specialist
Announcements
There are no new announcements at this time. Check back soon for updates.
Project Schedule
Design |
Quarter 3 (July - September) 2021 |
---|---|
Bidding |
Quarter 2 (April - June) 2022 |
Construction |
Quarter 3 (July - September) 2022 |
Completion (projected) |
Quarter 3 (July - September) 2024 |
Quarterly Reports
Quarter 3 (July - September) Report - Laurel CDC
Quarter 2 (April - June) Report - Laurel CDC
Quarter 1 (January - March) Report - Laurel CDC
Reports older than one (1) year are archived and available by request. To obtain an archived report, please email oaklandbuilt@ousd.org.
Presentations
Laurel CDC Project Budget Increase CBOC Meeting - June 9th, 2022 | Presentation
Laurel CDC Project Community Meeting - November 4th, 2021 | Presentation
Laurel CDC Project Community Meeting - June 24th, 2021 | Presentation