Laurel Child Development Center

Project Description

The project scope includes demolition of the existing CDC structure and replacement of a new CDC on the existing Laurel campus. The new CDC consists of four pre-school classrooms with the capacity to house 108 children. The front office includes a reception area, principal’s office, a parent resource center, staff workroom, warming kitchen, restrooms, and utility support spaces. Exterior site improvements include play yards, play structures, garden, artificial turf field and bio-swales. The design will meet energy and sustainability guidelines in the Collaborative for High Performance Schools (CHPS).

STATUS:

Complete

BUDGET:

$17.5M, Measures J and Y funding

ADDRESS:

3825 California St, Oakland, CA 94619

ARCHITECT:

Multistudio 

GENERAL CONTRACTOR:

Arntz Builders 

PROJECT TEAM:

Mary Ledezma, Project Manager

Imelda Meza, Project Engineer

Ray Bermudez, Engagement Specialist

Announcements

There are no new announcements at this time. Check back soon for updates.

Project Schedule

Design

Quarter 3 (July - September) 2021

Bidding

Quarter 2 (April - June) 2022

Construction

Quarter 3 (July - September) 2022

Completion (projected)       

Quarter 3 (July - September) 2024

Quarterly Reports

Quarter 3 (July - September) Report - Laurel CDC

Quarter 2 (April - June) Report - Laurel CDC

Quarter 1 (January - March) Report - Laurel CDC

 

Reports older than one (1) year are archived and available by request. To obtain an archived report, please email oaklandbuilt@ousd.org

 

Presentations

Laurel CDC Project Budget Increase CBOC Meeting - June 9th, 2022 | Presentation

Laurel CDC Project Community Meeting - November 4th, 2021 | Presentation

Laurel CDC Project Community Meeting - June 24th, 2021 | Presentation