Garfield Elementary School

Project Description
The primary focus of this project is to implement critical upgrades addressing life safety, accessibility, seismic resilience, structural integrity, and architectural enhancements. The scope will also include necessary fire life safety improvements and campus-wide safety upgrades to meet current standards and regulations. Additional elements of the scope will be further defined through an ongoing planning process, ensuring all upgrades are executed within the remaining allocated budget.
STATUS:
Design
BUDGET:
$70.7 M
FUNDING SOURCE:
Bond Measure Y
ADDRESS:
1640 22nd Avenue, Oakland, CA 94606
ARCHITECT:
GENERAL CONTRACTOR:
PROJECT TEAM:
John Esposito, Project Manager
Ray Bermudez, Engagement Specialist
Project Schedule
*Dates reflect the beginning of the phase.
| Planning | Quarter 1 (January - March) 2024 |
|---|---|
|
Design |
Quarter 3 (July - September) 2025 |
|
Bidding |
Quarter 3 (July - September) 2026 |
|
Construction (projected) |
Quarter 2 (January - March) 2027 |
|
Closeout (projected) |
Quarter 4 (October - December) 2028 |
Quarterly Reports
Quarter 2, 2025 (April - March) Report - Garfield Elementary School
Quarter 1, 2025 (January - March) Report - Garfield Elementary School
Reports older than one (1) year are available by request through the California Public Records Act (PRA). Please email your request to publicrecords@ousd.org.
Presentations
Garfield Project Community Input Session - October 2nd, 2024 | Presentation (English, Spanish), Meeting Summary
Garfield Project Community Input Session - April 23rd, 2024 | Presentation, Meeting Summary
*** The OUSD Facilities Planning and Management Department is committed to providing project updates and reports on a quarterly basis. Please check back each quarter for the latest project information.