Fremont High School (Phase 2)

Project Description
The project involves the demolition of existing portable classroom buildings and the installation of new, single-story modular classroom buildings, designed for improved space utilization and flexibility in educational settings. Additionally, the existing elevator system will be modernized to meet current building standards. The re-roofing scope encompasses the removal of the existing roofing materials and the installation of a new, energy-efficient roofing system designed to improve durability and performance. The existing parking lot will be renovated to improve drainage, pavement quality, and accessibility, incorporating ADA-compliant features.
STATUS:
Construction
BUDGET:
$15 M
FUNDING SOURCE:
Bond Measure J
ADDRESS:
4610 Foothill Blvd, Oakland, CA 94601
ARCHITECT:
GENERAL CONTRACTOR:
PROJECT TEAM:
JaQuan Cornish, Project Manager
Ray Bermudez, Engagement Specialist
Project Schedule
*Dates reflect the beginning of the phase.
| Planning | Quarter 3 (July - September) 2023 |
|---|---|
|
Design |
Quarter 1 (January - March) 2024 |
|
Bidding |
Quarter 4 (October - December) 2024 |
|
Construction (projected) |
Quarter 2 (January - March) 2025 |
|
Closeout (projected) |
Quarter 3 (July - September) 2026 |
Community Construction Updates
Quarterly Reports
Quarter 2, 2025 (April - June) Report - Fremont High School
Quarter 1, 2025 (January - March) Report - Fremont High School
Reports older than one (1) year are available by request through the California Public Records Act (PRA). Please email your request to publicrecords@ousd.org.