Fremont High School (Phase 2)

Project Description

The project involves the demolition of existing portable classroom buildings and the installation of new, single-story modular classroom buildings, designed for improved space utilization and flexibility in educational settings. Additionally, the existing elevator system will be modernized to meet current building standards. The re-roofing scope encompasses the removal of the existing roofing materials and the installation of a new, energy-efficient roofing system designed to improve durability and performance. The existing parking lot will be renovated to improve drainage, pavement quality, and accessibility, incorporating ADA-compliant features. 

STATUS:

Construction

BUDGET:

$15 M

FUNDING SOURCE:

Bond Measure J

ADDRESS:

4610 Foothill Blvd, Oakland, CA 94601

ARCHITECT:

Hibser Yamauchi Architects

GENERAL CONTRACTOR:

Cahill Contractors

PROJECT TEAM:

JaQuan Cornish, Project Manager

Ray Bermudez, Engagement Specialist

Project Schedule

*Dates reflect the beginning of the phase.

Planning Quarter 3 (July - September) 2023

Design 

Quarter 1 (January - March) 2024

Bidding 

Quarter 4 (October - December) 2024

Construction (projected)

Quarter 2 (January - March) 2025

Closeout (projected)

Quarter 3 (July - September) 2026

Community Construction Updates

Learn more about the construction updates that directly impact the surrounding community at the project site.
 
 

Quarterly Reports

Quarter 2, 2025 (April - June) Report - Fremont High School

Quarter 1, 2025 (January - March) Report - Fremont High School

Reports older than one (1) year are available by request through the California Public Records Act (PRA). Please email your request to publicrecords@ousd.org.

***The OUSD Facilities Planning and Management Department is committed to providing project updates and reports on a quarterly basis. Please check back each quarter for the latest project information.