Coliseum College Prep Academy

Project Description
The project includes the demolition of eight existing portable classroom units and the construction of a two-story building comprising 16 new classrooms. There will be 14 general education classrooms and two fully equipped science laboratories, designed with modern infrastructure to support advanced teaching technologies. The project also entails the construction of a new gymnasium building.
STATUS:
Design
BUDGET:
$68 M
FUNDING SOURCE:
Bond Measure Y
ADDRESS:
1390 66th Ave, Oakland, CA 94621
ARCHITECT:
GENERAL CONTRACTOR:
PROJECT TEAM:
Ellen Clements, Project Manager
Ray Bermudez, Engagement Specialist
Project Schedule
*Dates reflect the beginning of the phase.
| Planning | Quarter 3 (July - September) 2021 |
|---|---|
|
Design |
Quarter 3 (July - September) 2023 |
|
Bidding |
Quarter 1 (January - March) 2024 |
|
Construction (projected) |
Quarter 3 (July - September) 2026 |
|
Closeout (projected) |
Quarter 4 (October - December) 2027 |
Quarterly Reports
Quarter 1, 2025 (January-March) Report - Coliseum Cole College Prep Academy
Reports older than one (1) year are archived and available by request. To obtain an archived report, please email oaklandbuilt@ousd.org.
Presentations
CCPA Project Advisory Committee - September 19th, 2023 | Presentation
CCPA Project Community Input Session - October 10th, 2023 | Presentation
CCPA Project Community Input Session - December 19th, 2023 | Presentation (English, Spanish)
*** The OUSD Facilities Planning and Management Department is committed to providing project updates and reports on a quarterly basis. Please check back each quarter for the latest project information.