Coliseum College Prep Academy

CCPA

Project Description

 The project includes the demolition of eight existing portable classroom units and the construction of a two-story building comprising 16 new classrooms. There will be 14 general education classrooms and two fully equipped science laboratories, designed with modern infrastructure to support advanced teaching technologies. The project also entails the construction of a new gymnasium building.

STATUS:

Design

BUDGET:

$68 M

FUNDING SOURCE:

Bond Measure Y

ADDRESS:

1390 66th Ave, Oakland, CA 94621

ARCHITECT:

Shah Kawasaki Architects

GENERAL CONTRACTOR:

Overaa Construction

PROJECT TEAM:

Ellen Clements, Project Manager

Ray Bermudez, Engagement Specialist

Project Schedule

*Dates reflect the beginning of the phase.

Planning Quarter 3 (July - September) 2021

Design

Quarter 3 (July - September) 2023

Bidding

Quarter 1 (January - March) 2024

Construction (projected)

Quarter 3 (July - September) 2026

Closeout (projected)

Quarter 4 (October - December) 2027

Quarterly Reports

Quarter 1, 2025 (January-March) Report - Coliseum Cole College Prep Academy 

Reports older than one (1) year are archived and available by request. To obtain an archived report, please email oaklandbuilt@ousd.org

 

Presentations

CCPA Project Advisory Committee - September 19th, 2023 | Presentation

CCPA Project Community Input Session - October 10th, 2023 | Presentation

CCPA Project Community Input Session - December 19th, 2023 | Presentation (English, Spanish)

 

*** The OUSD Facilities Planning and Management Department is committed to providing project updates and reports on a quarterly basis. Please check back each quarter for the latest project information.