Claremont Middle School
Status: Substantially Complete
Location: Claremont Middle School, 5750 College Ave, Oakland, CA 94618
Budget: $21 M
Funding Source: Bond Measures B, J, and Y
Start Date: Quarter 4 (January - March) 2017
Completion Date: Quarter 3 (July - August) 2024
Scope: Construction of a new single-story 9,544 SF multi-purpose building and kitchen to include the construction of a cafeteria, kitchen, and stage platform, including associated support facilities, replacement of campus-wide intrusion alarm system, and installation of full-height permanent walls at three classrooms
Project Team:
Chastity Henderson, Project Engineer
Ray Bermudez, Engagement Specialist
Project Schedule
Planning | Quarter 3 (July- September) 2017 |
---|---|
Design | Quarter 4 (October- December) 2017 |
Bidding | Quarter 2 (April - June) 2022 |
Construction | Quarter 3 (July - September) 2022 |
Completion | Quarter 3 (April - June) 2024 |
Quarterly Reports
Quarter 1, 2025 (January - March) Report - Claremont
Reports older than one (1) year are archived and available by request. To obtain an archived report, please email oaklandbuilt@ousd.org.
Presentations
Claremont Project Status Update - February 4th, 2024 | Presentation
Claremont Project Status Update - September 21st, 2023 | Presentation