Claremont Middle School
Status: Substantially Complete
Location: Claremont Middle School, 5750 College Ave, Oakland, CA 94618
Budget: $21 M
Funding Source: Bond Measures B, J, and Y
Start Date: Quarter 4 (January - March) 2017
Completion Date: Quarter 3 (July - August) 2024
Scope: This project includes the construction of a vibrant new cafeteria, fully equipped kitchen, and a versatile stage platform, complete with all necessary support facilities. Additionally, the campus will benefit from a modernized intrusion alarm system for enhanced security, alongside the installation of sleek, full-height permanent walls in three classrooms to optimize space and functionality for students and staff.
Project Team:
Chastity Henderson, Project Engineer
Ray Bermudez, Engagement Specialist
Project Schedule
| Planning | Quarter 3 (July- September) 2017 |
|---|---|
| Design | Quarter 4 (October- December) 2017 |
| Bidding | Quarter 2 (April - June) 2022 |
| Construction | Quarter 3 (July - September) 2022 |
| Closeout | Quarter 3 (April - June) 2024 |
Quarterly Reports
Quarter 2, 2025 (April - June) Report - Claremont Middle School
Quarter 1, 2025 (January - March) Report - Claremont Middle School
Reports older than one (1) year are available by request through the California Public Records Act (PRA). Please email your request to publicrecords@ousd.org.
Presentations
Claremont Project Status Update - February 4th, 2024 | Presentation
Claremont Project Status Update - September 21st, 2023 | Presentation