Claremont Middle School

Status: Substantially Complete

Location: Claremont Middle School, 5750 College Ave, Oakland, CA 94618

Budget: $21 M

Funding Source: Bond Measures B, J, and Y

Start Date: Quarter 4 (January - March) 2017

Completion Date: Quarter 3 (July - August) 2024

Scope: This project includes the construction of a vibrant new cafeteria, fully equipped kitchen, and a versatile stage platform, complete with all necessary support facilities. Additionally, the campus will benefit from a modernized intrusion alarm system for enhanced security, alongside the installation of sleek, full-height permanent walls in three classrooms to optimize space and functionality for students and staff. 

Project Team:  

Chastity Henderson, Project Engineer

Ray Bermudez, Engagement Specialist

Project Schedule

Planning  Quarter 3 (July- September) 2017
Design Quarter 4 (October- December) 2017
Bidding Quarter 2 (April - June) 2022
Construction Quarter 3 (July - September) 2022
Closeout Quarter 3 (April - June) 2024

Quarterly Reports

Quarter 2, 2025 (April - June) Report - Claremont Middle School

Quarter 1, 2025 (January - March) Report - Claremont Middle School

Reports older than one (1) year are available by request through the California Public Records Act (PRA). Please email your request to publicrecords@ousd.org.

 

 

Presentations

Claremont Project Status Update - February 4th, 2024 | Presentation

Claremont Project Status Update - September 21st, 2023 | Presentation