Claremont Middle School

Status: Substantially Complete

Location: Claremont Middle School, 5750 College Ave, Oakland, CA 94618

Budget: $21 M

Funding Source: Bond Measures B, J, and Y

Start Date: Quarter 4 (January - March) 2017

Completion Date: Quarter 3 (July - August) 2024

Scope: Construction of a new single-story 9,544 SF multi-purpose building and kitchen to include the construction of a cafeteria, kitchen, and stage platform, including associated support facilities, replacement of campus-wide intrusion alarm system, and installation of full-height permanent walls at three classrooms

Project Team:  

Chastity Henderson, Project Engineer

Ray Bermudez, Engagement Specialist

Project Schedule

Planning  Quarter 3 (July- September) 2017
Design Quarter 4 (October- December) 2017
Bidding Quarter 2 (April - June) 2022
Construction Quarter 3 (July - September) 2022
Completion Quarter 3 (April - June) 2024

Quarterly Reports

Quarter 1, 2025 (January - March) Report - Claremont

 

Reports older than one (1) year are archived and available by request. To obtain an archived report, please email oaklandbuilt@ousd.org

Presentations

Claremont Project Status Update - February 4th, 2024 | Presentation

Claremont Project Status Update - September 21st, 2023 | Presentation